Certified Professional Public Buyer (CPPB) Practice Test

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the Certified Professional Public Buyer Test with our engaging materials. Access multiple choice questions with hints and detailed explanations. Start your journey to certification success today!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What happens when a contractor is ordered to accelerate work and incurs additional costs?

  1. It is considered a constructive change

  2. It is classified as a breach of contract

  3. It results in a penalty

  4. It is deemed a normal cost of business

The correct answer is: It is considered a constructive change

When a contractor is ordered to accelerate work and incurs additional costs, it is considered a constructive change. This is because the contractor was instructed to perform work outside the original contract terms, leading to added expenses that were not anticipated in the initial agreement. A constructive change occurs when a party unilaterally modifies the contract requirements, which can justify a claim for additional compensation due to the unforeseen costs associated with the accelerated work. In construction contracts, such adjustments may happen due to various reasons, including project urgency specified by the owner or unforeseen delays. Being classified as a constructive change allows the contractor to seek an equitable adjustment in their contract price or an extension of time, recognizing that the additional costs were not part of the original deal. Understanding this concept is critical in public purchasing and contracting, as it helps manage expectations and align responsibilities when project requirements evolve.